We are planning the next SRRA Quarterly meeting for the 26th January 2022. All being well we look forward to seeing you then.
Monthly Archives: October 2021
HS2 South Ruislip Utility Works
Latest from HS2 on road works in the South Ruislip area.
UTILITY WORKS IN SOUTH RUISLIP
Old Dairy Site
27th September – 15th December
Phase 1 Road narrows – Lane Closure
Phase 2 4-way lights with a loading bay suspension.
Phase 3 4-way lights with a loading bay suspension.
Phase 4 4-way lights
Phase 5 Road narrows parking bay suspension.
Engagements with local businesses has been confirmed
West End Road
29th November – 10th December
2-way traffic lights + pedestrian crossing (29/11 to 3/12)
4-Way traffic lights + pedestrian crossing (6/12 to 10/12)
Scope CCTV surveys
Station Approach / Long Drive
10 Jan – 22nd Jan 2022
TM operation 24 hours.
Traffic management2 way signals with footway closures assisted by 2 signalised crossing points.
Great Central Avenue closed in one direction throughout the duration of the works with suitable diversions provided.
IT IS HOPED THE DATES DON’T CHANGE BUT CHANGES HAVE BEEN FREQUENT LATELY