HS2 South Ruislip Utility Works

Latest from HS2  on road works in the South Ruislip area.

UTILITY WORKS IN SOUTH RUISLIP

Old Dairy Site

27th September – 15th December

Phase 1 Road narrows – Lane Closure

Phase 2 4-way lights with a loading bay suspension.

Phase 3 4-way lights with a loading bay suspension.

Phase 4 4-way lights

Phase 5 Road narrows parking bay suspension.

Engagements with local businesses has been confirmed

West End Road

29th November – 10th December

2-way traffic lights + pedestrian crossing (29/11 to 3/12)

4-Way traffic lights + pedestrian crossing (6/12 to 10/12)

Scope CCTV surveys

Station Approach / Long Drive

10 Jan – 22nd Jan 2022

TM operation 24 hours.

Traffic management2 way signals with footway closures assisted by 2 signalised crossing points.

Great Central Avenue closed in one direction throughout the duration of the works with suitable diversions provided.

IT IS HOPED THE DATES DON’T CHANGE BUT CHANGES HAVE BEEN FREQUENT LATELY